Why operators don't follow procedures

Operators set a procedure aside when it does not describe the work in front of them. I have watched that happen. The page was written for the file. The person on shift needs the next action.

29 CFR 1910.119(f) requires written operating procedures that give clear instructions for safely conducting activities in each covered process, consistent with the process safety information. 40 CFR 68.69 says the same thing for a Risk Management Program process in Program 3. A document can be long, numbered, and signed, and still fail that test at the equipment.

Put the action on the step

The usual draft starts with purpose, scope, references, a theory section, then steps, then a limit table in the back. That order suits the person building the file. It does not suit the operator who has a valve in hand.

The operator needs the action, the indication that shows the action worked, and the limit that says whether to continue. Those three belong on the step. A purpose statement three pages earlier does not help at 0200. A step that says "verify normal pressure" and leaves "normal" undefined sends the operator to memory.

1910.119(f)(2) requires the procedures to be readily accessible to employees who work in or maintain the process. A document that sits on a shelf and is never opened has met the shelf test and missed the work.

Write the steps in the order of the work

Steps that are true and in the wrong order get skipped. If the procedure says to line up a spare pump before it says to check that the discharge valve is shut, and the crew has always checked the valve first to avoid a water hammer, they will keep checking the valve first. They are avoiding a bad outcome the procedure failed to sequence.

Write the steps in the order the work is done. If two actions can happen in either order, say so. If one action has to come first because of a hazard, put the reason on the step, in one sentence. "Shut the discharge valve before you open the suction. An open discharge into a running spare will spin the pump backward." That is a step. "Ensure the pump is properly lined up" is a hope.

Temporary work is where the order breaks. A container change, a filter swap, a short-term lineup around a leaking valve: these are operating phases. The PSM list includes temporary operations. If that lineup lives only in the senior operator's head, the procedure does not cover the phase the rule names.

Put the limit on the step

1910.119(f)(1)(ii) and 68.69(a)(2) require operating limits, the consequences of deviation, and the steps required to correct or avoid deviation. Those three items are the decision the operator is making.

A step that says "maintain header pressure within limits" and points to a table sends the operator on a search. On a busy shift they use the number they remember. If that number is stale, the procedure has trained them to deviate.

Put the limit on the step. State the consequence in the operator's terms: what gets damaged, what stops, who gets exposed, what alarm comes in. Then state the corrective step, or the instruction to stop and call the supervisor. Copy the range from the process safety information. If the field notes have no limit, leave the gap and close it with the PSI and the people who run the unit. A guessed limit is a new hazard.

Update the page when the plant changes

A setpoint moves. A valve is renumbered. A temporary spool becomes permanent. 29 CFR 1910.119(l) requires the employer to address modifications to operating procedures before a change, and to update the procedures if the change affects them. 1910.119(f)(3) is the backstop: review as often as necessary so the procedures reflect current practice, and certify once a year that they are current and accurate.

Operators know when the page is wrong. After a few wrong pages, they stop checking the book. Tie the procedure update to the change. When the annual certification comes, compare the procedures to the changes, the piping and instrumentation drawings, and a walkdown. A signature on a list, with no comparison, certifies a stack of paper.

What I check before I call a draft done

The steps are numbered and in the order of the work. Each step says what to do and what indication shows it is done. Where a limit matters, the limit, the consequence of being outside it, and the corrective step are on that step. Where a safety system has to be in a stated condition before the next action, the step says so. Emergency shutdown says when shutdown is required and which qualified operators are responsible, which is the language of 1910.119(f)(1)(i) and of 40 CFR 68.69(a)(1).

Then the people who run the equipment walk the draft. They find the step that is out of order, the noun that names the wrong valve, and the limit that does not match the gage they read. Your subject-matter experts approve the procedure. I do not certify the process, and I do not replace that approval.

I write operating procedures for water, wastewater, and chemical plants. Your experts approve the procedure. Your facility does its own annual certification. This article is general information, not legal advice.